TDO Capital — Project Page

Indonesia's project pipeline, and how each project gets financed and built

A working guide for investors, contractors and project owners: announced, planned and in-tender projects from local governments, state-owned enterprises and the private sector — each with its owner, value where publicly stated, financing route and execution route, traced to a dated source.

Coverage: projects announced, planned or in tender 2025–2026 Compiled: 4 November 2026 Sources: government releases, KPBU register, company disclosures, national press
76 projects
in Bappenas' PPP Book 2026 across 10+ sectors (via Oct 2026 press summaries)
Rp408.68 tn
19 toll roads the Ministry of Public Works is preparing for KPBU auction in FY2026
Rp37.78 tn
PT SMI regional-loan commitments to local governments (outstanding Rp15.64 tn, Dec 2025)
100 GWp
national solar programme launched 25 Aug 2026 — first ~4.7 GWp bundle tender-ready

How these projects are financed

Six routes recur across the pipeline. Which one applies decides who can participate, what security is offered, and how the project owner gets repaid.

Financing route

KPBU / PPP

A private partner designs, builds, finances and operates the asset under a long concession (typically 20–50 years), repaid from user charges (tolls, water tariffs) or government availability payments. The Ministry of Finance can add a Project Development Facility (PDF) for preparation and a PT PII guarantee against government-performance risk.

Used by: central ministries, pemda and BUMD — water, hospitals, toll roads, street lighting below.

Financing route

PT SMI regional loans

PT Sarana Multi Infrastruktur, the Finance Ministry's infrastructure fund, lends directly to regional governments and public universities. Repayment is typically secured against central transfers (DAU/DBH). Faster and simpler than a capital-market issue, and currently the centre's preferred alternative to regional bonds at high yields.

Used by: Gianyar (Rp765 bn), Bogor and Surabaya water utilities, Lampung Utara roads.

Financing route

Regional bond / sukuk (Obda / Sukda)

A pemda issues bonds or sukuk on the IDX. Requires central approval (Finance Ministry and Home Affairs, plus Bappenas for bond/sukuk), a rating, and — under current rules — a tenor no longer than the regional head's remaining term. No region has yet issued; Jakarta's proposed programme below would be the first.

Used by: DKI Jakarta (proposed, not yet approved as of Oct 2026).

Financing route

Corporate bond / sukuk

A private or state-owned operator issues rated paper on the IDX to fund or refinance its concessions. Investors price the operator's credit, not the government's — Pefindo ratings and use-of-proceeds disclosure are the entry ticket.

Used by: PT Moya Indonesia — Rp2 tn bond + wakalah sukuk, listed July 2026.

Financing route

ODA & DFI loans

Concessional loans from development partners (JICA, ADB, Korea's EDCF via KEXIM) fund large government-executed works, often tied to international tender rules and joint-venture requirements for local firms.

Used by: MRT Jakarta East–West (JICA + ADB); Karian–Serpong conveyance (EDCF Korea).

Financing route

IPP equity + project debt

For power projects, a private developer (IPP) raises equity and limited-recourse debt against a long-term power purchase agreement with PLN. Danantara, the sovereign investment fund, can co-invest or act as backstop — its waste-to-energy programme uses 70% debt / 30% equity with a 30-year PLN offtake.

Used by: 100 GWp solar bundle, Cirata floating solar, Danantara PSEL programme.

How a project moves from announcement to construction

KPBU projects follow a regulated sequence. Knowing the stage tells an investor or contractor how close the money is — and when to engage.

STAGE 1

Preparation

Feasibility study, AMDAL and permits. Kemenkeu's PDF can fund this — Getaci toll road secured PDF support in June 2026 for a ~2-year preparation.

STAGE 2

Market sounding

The contracting authority (PJPK) tests investor appetite before tender. Wangaya Hospital and the three toll roads below are at this stage.

STAGE 3

Prequalification

Bidders are screened on financial and technical capacity. IA Moeis Hospital passed PQ with a single consortium (Plenary + Aspen Medical).

STAGE 4

Tender / auction

Solicited KPBU, unsolicited proposals (Ayung I water, Sleman lighting) or open government tender for loan- and budget-funded works.

STAGE 5

Signing & financial close

Concession agreement signed; lenders and guarantors (PT PII) close. Karian–Serpong conveyance contracts were signed 17 Oct 2025.

STAGE 6

Construction

Build period under the concession or works contract — e.g. 20 months for the Karian–Serpong pipes, completion targeted May 2027.

STAGE 7

Operation

The operator runs the asset for the concession term and is paid per the agreed tariff or availability payment — Jatiluhur I water has operated since Dec 2024.

The wider pipeline

Every other project found in the research, including operating reference projects that show how a financing model performs after completion. Filter by owner type or sector, or search by name or place.

Read with care — open questions

Compiled honestly: where sources disagree, both figures are shown on the entry rather than merged. The following were unresolved at the research date.

  • Jakarta's regional bond is proposed, not approved. As of 27–28 Oct 2026 the Finance Ministry had made no decision, citing high-rate risk, and cheaper alternatives (a PT SMI loan, APBN spending) were under active discussion. Its size is reported variously as Rp3.5 tn and Rp5.2–5.6 tn.
  • West Java's Rp3.4 tn PT SMI loan is not live pipeline. The DPRD agreed the proposal on 6 Oct 2026, but the Home Ministry gave no recommendation and the governor cancelled it — it is excluded from the pipeline above.
  • Hospital KPBU values conflict. IA Moeis is reported at ~Rp1.1 tn (AUD 70 m) in press coverage of the May 2025 Prabowo–Albanese meeting, while a PPP Book 2026 summary gives CAPEX of US$25.88 m. Wangaya is quoted at Rp800–900 bn locally vs US$36.36 m CAPEX in the same summary. Neither pair reconciles; both are shown.
  • Solar bundle figures conflict. PLTS Gilimanuk appears as 300 MWp in one source and 198 MWp (+666 MWh storage) in another, and the bundle as 7 projects / ~4.7 GWp vs 6 projects / 4.55 GWp. The programme's implementing regulation was still under inter-ministerial discussion in Sep 2026.
  • Waste-to-energy outcomes are partial. Phase-1 winners are confirmed for Bekasi, Denpasar Raya and Bogor Raya; reported plant capacity differs by source (1,000 vs 1,500 t/day), and Phase-2 winners — and Yogyakarta's Phase-1 outcome — were not confirmed in sources found.
  • Tender deadlines were not verified live. LPSE/LKPP portal status for individual packages (e.g. Gianyar road works, Batang waste plant) is reported from dated sources, not checked on the portal at the research date. Confirm deadlines on LPSE before bidding.
  • Other flagged discrepancies: Jatiluhur I value Rp1.75 tn vs Rp1.675 tn; Semarang Barat ~Rp1.2046 tn vs a Rp0.4 tn PII guarantee figure; Karian–Serpong network length 43 km vs 59.6 km; MRT East–West operations targeted 2031 vs 2032; Kendal SEZ area 2,200 vs 2,700 ha.